A house renovation can take anything from a couple of weeks to six months or more, depending on how much you're doing. As a rough guide, a bathroom refresh often takes two to three weeks and a full bathroom remodel four to five, a new kitchen around six to eight weeks, and a whole-house renovation of a Victorian terrace around five to six months once work starts. Design, approvals and lead times for materials can add weeks or months before the builders arrive. Here's how the time breaks down and what you can do to keep your project on track.

Typical timescales by type of project

Every house is different, so treat these as typical ranges reported in UK renovation guidance rather than promises. Your builder should give you a programme for your own project once they've seen it.

  • Bathroom refresh (like-for-like, no layout change): about two to three weeks.
  • Full bathroom remodel (new pipework, waterproofing, layout or structural changes): about four to five weeks.
  • Kitchen: around six to eight weeks for most projects; a simple like-for-like replacement can be closer to a month.
  • Whole-house renovation of a typical Victorian terrace: around five to six months, assuming good planning and a relatively straightforward scope. Larger or more complex projects take longer.

The stages that make up the time

Before work starts

The time before builders arrive is often underestimated. It can include:

  • Design – drawings from an architect or designer, and structural calculations if walls are being removed.
  • Planning permission, if needed – councils normally aim to decide straightforward applications within 8 weeks of a valid application (13 weeks for unusually large or complex ones). Many internal renovations don't need planning permission, but changes to the outside of a house in a conservation area often do.
  • Building regulations – a full plans application is usually decided within about five weeks; with a building notice, work can usually start once the notice has been accepted, often within a couple of days.
  • Party wall notices, if your work affects a shared wall – at least two months' notice for work to a party wall, or one month for excavation near a neighbour's foundations.
  • Quotes and lead times – getting quotes, choosing a builder and waiting for their start date, plus delivery times for kitchens, windows and made-to-measure items.

During the build

A whole-house renovation usually runs in this order: strip-out and structural work; repairs to make the house weathertight; first-fix electrics, plumbing and heating; plastering and screeding; second fix; kitchen, bathrooms, joinery and flooring; and finally decorating. Some stages overlap, but many can't start until the one before is finished. Plaster and screed, for example, need time to dry before finishes go on.

What causes delays

The most common reasons renovations overrun are:

  • Hidden problems – rotten joists, old wiring, damp or poor previous alterations found once walls and floors are opened up. These are especially common in older houses.
  • Late decisions – choosing tiles, kitchens or fittings during the build rather than before it, or changing your mind once work has started.
  • Long lead times – items ordered too late, or made-to-measure pieces that take weeks to produce.
  • Trade availability – when one trade runs late, those booked after them can be pushed back.
  • Inspections and approvals – building control inspections that weren't booked at the right time, or approvals that weren't in place before starting.
  • Access and logistics – in London, parking, deliveries, skip and scaffold licences all need planning.

How to keep your renovation on schedule

  1. Survey before you plan – especially in a period property, find out about the condition of the house early.
  2. Decide before you start – choose kitchens, bathrooms, tiles, flooring and fittings, and order long-lead items, before work begins.
  3. Get approvals in place – planning, building regulations and party wall notices should be sorted before the start date.
  4. Agree a written programme – ask your builder for the order of works and the key dates.
  5. Allow a contingency – build some spare time into your plans for the unexpected, particularly in older houses.
  6. Keep communicating – regular updates and quick answers to questions keep the work moving.

Can you stay at home during a renovation?

For a single room, usually yes. For a whole-house renovation, or when the kitchen and only bathroom are out of action at the same time, many people move out for some or all of the work. Phasing the work room by room makes staying possible, but it usually makes the overall project longer. Our guide to renovating a Victorian terrace covers the order of works in more detail.

Planning a renovation in South London?

Costa Construction renovates homes across South London, including Balham, Clapham, Streatham and Tooting. We'll visit, talk through what's involved and give you a written quote and an idea of timings for your project. Call 07340042048 or contact us.

Frequently asked questions

How long does it take to renovate a whole house?

Once work starts, a whole-house renovation of a typical Victorian terrace often takes around five to six months. Larger or more complex projects take longer, and design and approvals add time before work begins.

How long does a kitchen renovation take?

Most kitchen renovations take around six to eight weeks; a simple like-for-like replacement can be closer to a month.

How long does a bathroom renovation take?

A like-for-like bathroom refresh often takes two to three weeks, while a full remodel with new pipework or layout changes takes around four to five weeks.

How long does planning permission take?

Councils normally aim to decide straightforward planning applications within 8 weeks of receiving a valid application, or 13 weeks for unusually large or complex ones.